Stage/workstream |
Pre-planning / Planning |
Shadow |
Vesting day and beyond (specific activity in this phase will be determined by the new unitary authorities) |
---|---|---|---|
Programme management office |
Resource and mobilise PMO |
|
Oversee implementation of target operating model and complete delivery of implementation plans for all services |
Resource and mobilise delivery workstreams |
|
||
Establish and operate programme governance structures, oversight and assurance |
|||
Resource planning for shadow period activity |
|||
Coordinate development of target operating model and detailed transition/implementation planning for all services |
|||
|
Transformation programme mobilisation |
||
Communications and engagement |
Develop and deliver transition external communications and engagement strategy |
Vesting day and post vesting day communications (internal and external) |
|
Develop and deliver transition internal communications and engagement strategy |
|||
|
Develop Vesting day communications strategy (internal and external |
||
|
Brand development |
Brand roll out |
|
|
|
Evaluation and feedback |
|
Legal, governance and electoral |
Structural change orders and other legal advice and support |
Ensure legal compliance on Vesting Day |
|
Prepare and run unitary elections |
Creation of shadow authorities, shadow council appointments and structures |
||
Shadow member induction |
Ongoing member training |
||
Establish data governance / records management protocols |
Develop constitutions for the new authorities, including arrangements for scrutiny, standards, risk management, and independent assurance |
Implement constitution and arrangements for scrutiny, standards, risk management, and independent assurance |
|
Plan for governance arrangements of Local Authority owned companies and their specific transitional requirements |
Deliver arrangements for transition of Local Authority owned companies |
||
Plan community governance and empowerment approach |
Undertake community governance reviews as appropriate and or run community empowerment structures in shadow form |
Implement structures for community governance and empowerment |
|
Finance, debt, procurement and revenues and benefits |
Formal collation and review of baseline information and development of workstream plan including risk management |
MTFPs and budget setting for the new authorities (2027/28) |
MTFPs and budget setting for 2028/29) |
Plan for and where possible deliver alignment of financial, procurement, and revenues and benefits processes, procedures and systems |
Deliver arrangements for transition of financial, procurement and revenues and benefits |
||
|
Consolidation of financial arrangements including Council Tax equalisation, HRA, service budgets, banking, transactions, payments and receipts |
2026/27 accounts closure |
|
Develop Debt and Treasury Management transition plan |
Deliver Debt and Treasury Management transition plan |
||
Human resources and organisational development |
Formal collation and review of baseline information and development of workstream plan including risk management |
Workforce planning / organisation design for new authorities and change management strategy |
|
Staff support, wellbeing, and training (including change management / resilience) |
|||
Trade union consultation and negotiation |
|||
Resourcing plan for shadow period roles and recruitment |
Appointment of statutory officers and senior management teams to new authorities |
Formal appointment of other layers of staffing |
|
Identify and where possible progress shared posts for appropriate lower-tier authority vacancies
|
|||
|
Arrangements for payroll, terms and conditions and TUPE |
Plan for and implement harmonisation of terms and conditions |
|
Develop health and safety transition plan |
Deliver health and safety transition plan |
||
|
Develop and embed organisation values, culture and ways of working for new authorities |
||
Plan for and where possible deliver alignment of HR processes, procedures and systems |
Deliver arrangements for transition of HR processes, procedures and systems |
||
Data, IT and Systems |
Formal collation and review of baseline information and development of workstream plan including contracts and risk management |
Agree and deliver arrangements for cyber security, disaster recovery and business continuity |
Ensure compliance on Vesting Day |
Establish data management and sharing protocols |
Deliver arrangements for consolidation and transition of data, ICT processes, procedures and systems |
||
Plan for and where possible deliver alignment and consolidation of ICT processes, procedures and systems |
|||
|
Develop single platform for new authorities including web, email and telephony (staff/members/public) |
Launch on Vesting Day |
|
|
|
Develop digital strategy |
|
Assets and Estate |
Formal collation and review of baseline information and development of workstream plan including risk management |
|
|
Plan for and where possible deliver alignment and consolidation of asset management processes, policies and systems |
Deliver arrangements for alignment and consolidation of asset management processes, policies and systems |
||
Review asset database to inform asset rationalisation, investment and disposal strategy |
Finalise and then deliver asset rationalisation, investment and disposal strategy |
||
Transition to new operational asset bases (offices, customer contact points, depots) |
|||
Customer contact |
Develop customer contact transition plan |
Develop and communicate abut single platform for new authorities including web, email and telephony (staff/members/public) |
Launch on Vesting Day |
Plan for and where possible deliver alignment of customer contact processes, policies and systems including complaints handling |
Deliver arrangements for alignment and consolidation of customer contact processes, policies and systems |
||
Community governance and neighbourhood empowerment |
Options assessment and engagement in relation to future community governance and neighbourhood empowerment structures |
Progress to deliver preferred option for informal and/or formal community empowerment structures |
|
Devolution |
Early discussions and agreement with government about process and timetable for MSA establishment |
Commence formal process for establishment of MSA. Note that this will require establishment of a dedicated PMO and associated delivery workstreams |
Possible Mayoral elections May 2027 |