Play area improvements

In October 2023 we announced over £1 million investment into our play parks. We are now taking this forward and over the coming months several play areas across the borough will have replacement items installed, or a complete replacement. Below is a list of play areas due to have work with scheduled start dates – these are subject to contractor availability, weather conditions etc but any changes will be updated on this webpage.

Table of works

Play area Type of works Scheduled start date
Gogmore Farm Surfacing repairs 2 April 2024
Chertsey Rec Replacement items 15 April 2024
King George V Complete replacement 15 April 2024
Beomonds Complete replacement 17 April 2024
Pooley Green (Toddler) Complete replacement 22 April 2024
Surrey Towers Complete replacement 29 April 2024
Hythe Park (Junior) Replacement and additional items 7 May 2024
Manorcroft Park Complete replacement 7 May 2024
Sayes Court Replacement items 13 May 2024
Sumner Place Replacement items 13 May 2024
Victory Park Replacement items 13 May 2024
Heathervale Park Replacement items 20 May 2024
Walton Leigh Replacement items 20 May 2024
Woodham Lodge Replacement items 20 May 2024
Abbeyfields Replacement items 27 May 2024
Charta Road Replacement items 27 May 2024
Edgell Close Replacement items 27 May 2024
Englefield Green TBC TBC
Hamm Moor Complete replacement 10 June 2024
(approx. 4 week)
Runnymede Pleasure Grounds TBC TBC

Did you know if you have any issues within our parks you can report them directly to use through our reporting form

Report a park issue